Oracle released Primavera P6 Version 21 PPM for download from their eDelivery web site in late 2021.
Oracle has published a tool that you may use to see the enhancement that have been introduced into P6 by comparing two different versions. This is the link to the “Oracle Primavera P6 Cumulative Feature Overview”
Aim
The aim of this paper is to explain the main functional changes that users will see in the Oracle Primavera P6 PPM V21.12 added since the release of P6 PPM V20.12.
The Oracle Cumulative Feature Overview file states “When you export to Primavera XML, Price Per Unit data for assignments is included in the export file.”
This statement is a little misleading and I will now explain what I have found. Please note that there are many options that affect how data is imported into a P6 database, but I have used the default options in my tests. You may receive different results with different options. Lastly this is a very difficult topic to document and understand.
Version 20 XML Import and Export Resource Unit Rate Issue
In summary the current issue with importing an P6 XML project file into Version 20 and earlier is that the imported project may calculate different cost to the project that was exported and the issue is outlined below in my example. The issue occurs when:
For example,
It was then exported as an XER and XML and both the resource and project deleted and the project imported:
Thus, the imported project has incorrect activity costs.
Version 21 Changes
When the project was exported and imported into a Version 21 database it behaved in a similar way as in Version 20, but with one minor change. The change that I found in Version 21 was that:
Assignment Cost are Exported Conclusion and Solution
My testing indicates that the Activity Resource assignment Unit Rate being changed on the import of an XML to the Resource table Unit Rate has not been fixed with this enhancement.
If you want the costs to remain the same when importing an XML file, then the Resource table Unit Rates must be the same as the Activity assigned resource Unit Rates when a file is exported and you must be careful when you import an XML project into a database that the resource already exists in.
There is one slight change with Version 21 and that is the imported project costs are always calculated based on the exported Resource table unit rates, but this Version is still not using the exported assigned activity Unit Rate.
If you did not understand my text above and you wish to import XML projects to calculate the same as exported projects then always ensure that the Resource table Unit Rate in the export database and import database is the same as all Activity resource assignment Unit Rate, or use XER files.
Earn 25% commission when your network purchase Uplyrn courses or subscribe to our annual membership. It’s the best thing ever. Next to learning, of course.
This is a great enhancement as P6 usually picks the wrong time when setting Actual dates, Constraints, Suspend and Resume dates when the time is not set to be displayed from the User Preferences.
When you import projects from a Primavera XML file, you can choose whether to retain relationships between activities in the project and those in external projects.
P6 Version 20 XML Project Import Options (see picture on the right).
Option added to P6 Version21 (see picture on the right).
On the right are three projects, MP1, MP2 and MP3 with their single activities linked.
The second project, MP2 was exported, deleted and imported with each of the three options.
Note: External Early Start and External Early Finish dates are not set with this update thus allows you to import a project and NOT set External Dates when the project have External Relationships.
The Admin Preferences, Options has introduced a Cost Spread option.
This changes how the cost spreads for resources and role rates are reflected in the Resource Usage Spreadsheet and Profile, Activity Usage Spreadsheet and Profile, Tracking View, Resource Assignments window, and Activity Usage Spreadsheets and Profiles, Publishing and Reports.
In earlier versions when a resource rate changed during the duration of an activity then P6 took an average rate for the resource over the activity duration which gave an incorrect cashflow.
There is a new toolbar in Version 21 titled Activity Critical Path.
The Oracle Cumulative Feature Overview file states:
To aid in the resolution of delayed critical paths before they become project over-runs, P6 Professional can show:
P6 Version 20 and earlier supports more relationship types than P6 Version 21.
Projects imported into P6 Version 21 from earlier versions bring in and acknowledge the old relationship types but these Start Milestone FS and Finish Milestone FF cannot be set in Version 21.
If you want to learn more about Planning and Control with Microsoft Project, please check out my online course here.
Leave your thoughts here...
All Comments
Reply